Musgravite Solar (27INR0198)

Musgravite Solar is a 100.6 MW solar interconnection project in Henderson, Texas with a current status of operational. It is proposed to connect at Tap 138 kV (6855) Coffee - (6849) New York..

100.6 MWCapacity
OperationalStatus
HendersonMarket
SolarTechnology

Project facts

Canonical nameMusgravite Solar
Queue ID27INR0198
Statusoperational
Source statusSS Completed, FIS Completed, IA
MarketHenderson
TechnologySolar
Capacity100.6 MW
StateTexas
CountyHenderson
Point of interconnectionTap 138 kV (6855) Coffee - (6849) New York.
Requested (queue) date2024-03-22
Proposed in-service date
Operational date2027-11-01
Withdrawn date
DeveloperBT Thompson Solar, LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-28

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata