National Tac Plant 115kV (Customer-owned) (J3237)

National Tac Plant 115kV (Customer-owned) is a 86.0 MW wind interconnection project in Itasca, Minnesota with a current status of withdrawn. It is proposed to connect at National Tac Plant 115kV (Customer-owned).

86.0 MWCapacity
WithdrawnStatus
Market
WindTechnology

Project facts

Canonical nameNational Tac Plant 115kV (Customer-owned)
Queue IDJ3237
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyWind
Capacity86.0 MW
StateMinnesota
CountyItasca
Point of interconnectionNational Tac Plant 115kV (Customer-owned)
Requested (queue) date2024-04-09
Proposed in-service date2028-06-09
Operational date2028-06-09
Withdrawn date2025-07-30
Developer
Utility / transmission ownerMINNESOTA POWER INC.

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.