ND Queue Project MPC01600 — Wind in Oliver, North Dakota

ND Queue Project MPC01600 — Wind in Oliver, North Dakota is a 399.6 MW wind interconnection project in Oliver, North Dakota with a current status of withdrawn. It is proposed to connect at Center - Red River Valley 345 kV Line.

399.6 MWCapacity
WithdrawnStatus
NDMarket
WindTechnology

Project facts

Canonical nameND Queue Project MPC01600 — Wind in Oliver, North Dakota
Queue IDMPC01600
Statuswithdrawn
Source status—
MarketND
TechnologyWind
Capacity399.6 MW
StateNorth Dakota
CountyOliver
Point of interconnectionCenter - Red River Valley 345 kV Line
Requested (queue) date2008-11-24
Proposed in-service date2012-03-01
Operational date—
Withdrawn date—
Developer—
Utility / transmission ownerMinnkota Power Cooperative

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_project—withdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-10-11

Provenance: minnkota-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.