Oliver County, North Dakota — Interconnection Projects
The interXdata warehouse tracks 19 interconnection projects in Oliver, North Dakota, representing 4,612 MW of requested capacity.
19Total projects
2Active
8Operational
9Withdrawn
4,612 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Wind | 14 | 2,624 MW |
| Other | 3 | 1,189 MW |
| Coal | 1 | 600 MW |
| Solar | 1 | 200 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| MISO Queue Project G581 — Coal in Oliver, North Dakota | G581 | Coal | 600.0 MW | withdrawn | Oliver, North Dakota |
| MISO Queue Project H082 — Wind in Oliver, North Dakota | H082 | Wind | 500.0 MW | withdrawn | Oliver, North Dakota |
| Milton R Young | 2823_2 | Other | 477.0 MW | operational | Oliver, North Dakota |
| ND Queue Project MPC01300 — Other in Oliver, North Dakota | MPC01300 | Other | 455.0 MW | operational | Oliver, North Dakota |
| ND Queue Project MPC01600 — Wind in Oliver, North Dakota | MPC01600 | Wind | 399.6 MW | withdrawn | Oliver, North Dakota |
| ND Queue Project MPC04000 — Wind in Oliver, North Dakota | MPC04000 | Wind | 300.0 MW | active | Oliver, North Dakota |
| Milton R Young | 2823_1 | Other | 257.0 MW | operational | Oliver, North Dakota |
| Basin Electric 230 kV | GEN-2016-004 | Wind | 202.0 MW | active | Oliver, North Dakota |
| MISO Queue Project J511 — Wind in Oliver, North Dakota | J511 | Wind | 200.0 MW | withdrawn | Oliver, North Dakota |
| Coyote | J3182 | Solar | 200.0 MW | withdrawn | Oliver, North Dakota |
| Square Butte 230 kV Substation East | J2080 | Wind | 200.0 MW | withdrawn | Oliver, North Dakota |
| Oliver Wind IV | 67502_GEN4 | Wind | 198.8 MW | operational | Oliver, North Dakota |
| Square Butte 230 kV Substation East | J1888 | Wind | 175.0 MW | withdrawn | Oliver, North Dakota |
| ND Queue Project MPC02400 — Wind in Oliver, North Dakota | MPC02400 | Wind | 149.5 MW | withdrawn | Oliver, North Dakota |
| ND Queue Project MPC02100 — Wind in Oliver, North Dakota | MPC02100 | Wind | 100.0 MW | operational | Oliver, North Dakota |
| FPL Energy Oliver Wind I LLC | 56392_1 | Wind | 50.6 MW | operational | Oliver, North Dakota |
| MISO Queue Project G502 — Wind in Oliver, North Dakota | G502 | Wind | 50.0 MW | operational | Oliver, North Dakota |
| MISO Queue Project G659 — Wind in Oliver, North Dakota | G659 | Wind | 50.0 MW | withdrawn | Oliver, North Dakota |
| FPL Energy Oliver Wind II LLC | 56573_2 | Wind | 48.0 MW | operational | Oliver, North Dakota |
Top developers
Developer attribution is not yet resolved for this set.
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; minnkota-oasis; MISO — generator interconnection queue; Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Get an alert when a new project is proposed in Oliver County.
Start tracking with interXdata