New 161kV substation looping in OPPD 161kV lines S1211 to S1220 and S1211 to S1299 (GEN-2021-039)

New 161kV substation looping in OPPD 161kV lines S1211 to S1220 and S1211 to S1299 is a 100.0 MW battery interconnection project in Douglas, Nebraska with a current status of active. It is proposed to connect at New 161kV substation looping in OPPD 161kV lines S1211 to S1220 and S1211 to S1299.

100.0 MWCapacity
ActiveStatus
NEMarket
BatteryTechnology

Project facts

Canonical nameNew 161kV substation looping in OPPD 161kV lines S1211 to S1220 and S1211 to S1299
Queue IDGEN-2021-039
Statusactive
Source statusIA FULLY EXECUTED/ON SCHEDULE
MarketNE
TechnologyBattery
Capacity100.0 MW
StateNebraska
CountyDouglas
Point of interconnectionNew 161kV substation looping in OPPD 161kV lines S1211 to S1220 and S1211 to S1299
Requested (queue) date2021-04-30
Proposed in-service date2030-05-31
Operational date
Withdrawn date
Developer
Utility / transmission ownerOPPD

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectactivehigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.