New 161kV substation looping in OPPD 161kV lines S1211 to S1220 and S1211 to S1299 (GEN-2021-039)
New 161kV substation looping in OPPD 161kV lines S1211 to S1220 and S1211 to S1299 is a 100.0 MW battery interconnection project in Douglas, Nebraska with a current status of active. It is proposed to connect at New 161kV substation looping in OPPD 161kV lines S1211 to S1220 and S1211 to S1299.
Project facts
| Canonical name | New 161kV substation looping in OPPD 161kV lines S1211 to S1220 and S1211 to S1299 |
|---|---|
| Queue ID | GEN-2021-039 |
| Status | active |
| Source status | IA FULLY EXECUTED/ON SCHEDULE |
| Market | NE |
| Technology | Battery |
| Capacity | 100.0 MW |
| State | Nebraska |
| County | Douglas |
| Point of interconnection | New 161kV substation looping in OPPD 161kV lines S1211 to S1220 and S1211 to S1299 |
| Requested (queue) date | 2021-04-30 |
| Proposed in-service date | 2030-05-31 |
| Operational date | — |
| Withdrawn date | — |
| Developer | — |
| Utility / transmission owner | OPPD |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-31 | new_project | — | active | high |
Explore related data
Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata