Newhart-Potter County 230 kV (GEN-2017-012)

Newhart-Potter County 230 kV is a 201.6 MW wind interconnection project in Castro County, Texas with a current status of withdrawn. It is proposed to connect at Newhart-Potter County 230 kV.

201.6 MWCapacity
WithdrawnStatus
TXMarket
WindTechnology

Project facts

Canonical nameNewhart-Potter County 230 kV
Queue IDGEN-2017-012
Statuswithdrawn
Source statusWITHDRAWN
MarketTX
TechnologyWind
Capacity201.6 MW
StateTexas
CountyCastro County
Point of interconnectionNewhart-Potter County 230 kV
Requested (queue) date2017-05-12
Proposed in-service date
Operational date
Withdrawn date2020-12-07
Developer
Utility / transmission ownerSPS

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-28
Data last materially changed2026-08-28
Page data generated2026-08-28

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.