NorCal FPV 1 (Pond 2) (68787_23889)

NorCal FPV 1 (Pond 2) is a 1.8 MW solar interconnection project in Alameda, California with a current status of active.

1.8 MWCapacity
ActiveStatus
CISOMarket
SolarTechnology

Project facts

Canonical nameNorCal FPV 1 (Pond 2)
Queue ID68787_23889
Statusactive
Source status(V) Under construction, more than 50 percent complete
MarketCISO
TechnologySolar
Capacity1.8 MW
StateCalifornia
CountyAlameda
Point of interconnection
Requested (queue) date
Proposed in-service date2026-08-01
Operational date
Withdrawn date
Developer
Utility / transmission ownerNorCal FPV 1, LLC

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-02new_projectactivehigh

Explore related data

Source last checked2026-08-03
Data last materially changed2026-08-03
Page data generated2026-08-27

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned). Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata