NV Queue Project Company 223 — Battery in Clark, Nevada

NV Queue Project Company 223 — Battery in Clark, Nevada is a 20.0 MW battery interconnection project in Clark, Nevada with a current status of withdrawn. It is proposed to connect at Highland 12.47 kV.

20.0 MWCapacity
WithdrawnStatus
NVMarket
BatteryTechnology

Project facts

Canonical nameNV Queue Project Company 223 — Battery in Clark, Nevada
Queue IDCompany 223
Statuswithdrawn
Source statusWithdrawn
MarketNV
TechnologyBattery
Capacity20.0 MW
StateNevada
CountyClark
Point of interconnectionHighland 12.47 kV
Requested (queue) date2022-06-29
Proposed in-service date2025-02-20
Operational date
Withdrawn date
Developer
Utility / transmission ownerNV Energy (Nevada Power / Sierra Pacific Power)

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-03new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-28

Provenance: nvenergy-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.