Clark County, Nevada — Interconnection Projects

The interXdata warehouse tracks 439 interconnection projects in Clark, Nevada, representing 74,811 MW of requested capacity.

439Total projects
72Active
191Operational
152Withdrawn
74,811 MWRequested capacity

Technology mix

TechnologyProjectsRequested capacity
Solar+Battery6719,338 MW
Solar18218,567 MW
Battery7817,183 MW
Gas9315,002 MW
Other152,676 MW
Wind42,046 MW

Projects

ProjectQueue IDTechnologyCapacityStatusLocation
SEARCHLIGHT 1126Wind1,500.0 MWwithdrawnClark, Nevada
NV Queue Project Company 257 — Battery in Clark, NevadaCompany 257Battery800.0 MWactiveClark, Nevada
ARIDA 2 SOLAR FARM1647Solar+Battery700.0 MWactiveClark, Nevada
Gemini Solar Hybrid63352_ARBE1Solar690.0 MWoperationalClark, Nevada
COPPER MOUNTAIN II237Gas634.0 MWwithdrawnClark, Nevada
COPPER MOUNTAIN II ALTERNATE263Gas634.0 MWwithdrawnClark, Nevada
COPPER MOUNTAIN PROJECT56Gas634.0 MWwithdrawnClark, Nevada
NV Queue Project Company 201 — Solar+Battery in Clark, NevadaCompany 201Solar+Battery600.0 MWsuspendedClark, Nevada
SUNVALE SOLAR FARM1524Solar+Battery600.0 MWwithdrawnClark, Nevada
EL DORADO VALLEY GENERATION605Gas600.0 MWwithdrawnClark, Nevada
NV Queue Project Company 200 — Solar+Battery in Clark, NevadaCompany 200Solar+Battery600.0 MWactiveClark, Nevada
NV Queue Project Company 224 — Solar+Battery in Clark, NevadaCompany 224Solar+Battery600.0 MWsuspendedClark, Nevada
BIGHORN145Gas591.0 MWwithdrawnClark, Nevada
RELIANT ENERGY BIGHORN71Gas591.0 MWwithdrawnClark, Nevada
Reed Meadow2245Battery565.8 MWwithdrawnClark, Nevada
SANDY VALLEY PHASE II SEGS889Gas540.0 MWwithdrawnClark, Nevada
Grapevine 22228Battery505.1 MWwithdrawnClark, Nevada
NV Queue Project 25-00385 — Battery in Clark, Nevada25-00385Battery500.0 MWwithdrawnClark, Nevada
NV Queue Project 25-00418 — Battery in Clark, Nevada25-00418Battery500.0 MWactiveClark, Nevada
West Queue Project Q88 — Solar+Battery in Clark, NevadaQ88Solar+Battery500.0 MWactiveClark, Nevada
MOSEY2148Solar+Battery500.0 MWactiveClark, Nevada
NV Queue Project 25-00420 — Solar+Battery in Clark, Nevada25-00420Solar+Battery500.0 MWactiveClark, Nevada
NV Queue Project Company 250 — Other in Clark, NevadaCompany 250Other500.0 MWactiveClark, Nevada
NV Queue Project Company 251 — Other in Clark, NevadaCompany 251Other500.0 MWsuspendedClark, Nevada
West Queue Project NC5-002 — Other in Clark, NevadaNC5-002Other499.0 MWactiveClark, Nevada
NV Queue Project Company 218 — Solar+Battery in Clark, NevadaCompany 218Solar+Battery460.0 MWwithdrawnClark, Nevada
ARIDA 3 SOLAR FARM1795Solar+Battery450.0 MWactiveClark, Nevada
SLOAN ENERGY CENTER1653Solar+Battery448.0 MWwithdrawnClark, Nevada
NV Queue Project Company 148 — Solar in Clark, NevadaCompany 148Solar440.0 MWwithdrawnClark, Nevada
NV Queue Project Company 151 — Solar in Clark, NevadaCompany 151Solar440.0 MWoperationalClark, Nevada
NV Queue Project Company 180 — Solar+Battery in Clark, NevadaCompany 180Solar+Battery425.0 MWwithdrawnClark, Nevada
NV Queue Project Company 191 — Solar+Battery in Clark, NevadaCompany 191Solar+Battery425.0 MWsuspendedClark, Nevada
PURPLE SAGE ENERGY CENTER1800Solar+Battery400.0 MWactiveClark, Nevada
NV Queue Project 251107000000 — Battery in Clark, Nevada251107000000Battery400.0 MWactiveClark, Nevada
JEAN LAKE SOLAR234Gas400.0 MWwithdrawnClark, Nevada
West Queue Project Q115 — Battery in Clark, NevadaQ115Battery400.0 MWactiveClark, Nevada
West Queue Project Q116 — Battery in Clark, NevadaQ116Battery400.0 MWactiveClark, Nevada
NV Queue Project Company 212 — Battery in Clark, NevadaCompany 212Battery400.0 MWsuspendedClark, Nevada
NV Queue Project Company 194 — Solar+Battery in Clark, NevadaCompany 194Solar+Battery400.0 MWwithdrawnClark, Nevada
NV Queue Project Company 226 — Battery in Clark, NevadaCompany 226Battery400.0 MWsuspendedClark, Nevada
NV Queue Project Company 206 — Battery in Clark, NevadaCompany 206Battery400.0 MWsuspendedClark, Nevada
BULLHEAD SOLAR1648Solar+Battery400.0 MWwithdrawnClark, Nevada
Rough Hat63782_RH1Solar400.0 MWactiveClark, Nevada
NEVADA MOHAVE SOLAR1218Solar400.0 MWwithdrawnClark, Nevada
NV Queue Project 251107000001 — Battery in Clark, Nevada251107000001Battery400.0 MWactiveClark, Nevada
Purple Sage Energy Center68209_PSGPVSolar400.0 MWactiveClark, Nevada
Purple Sage Energy Center68209_PSGBSBattery400.0 MWactiveClark, Nevada
NV Queue Project 25-00384 — Battery in Clark, Nevada25-00384Battery400.0 MWwithdrawnClark, Nevada
Gemini Solar Hybrid63352_ARPV1Battery380.0 MWoperationalClark, Nevada
NV Queue Project Company 228 — Battery in Clark, NevadaCompany 228Battery380.0 MWsuspendedClark, Nevada
SOUTHLAND1336Solar375.0 MWwithdrawnClark, Nevada
Arida Solar (Hybrid)63841_BESSBattery370.0 MWactiveClark, Nevada
Arida Solar (Hybrid)63841_ARIDASolar370.0 MWactiveClark, Nevada
ARIDA SOLAR FARM1522Solar+Battery370.0 MWactiveClark, Nevada
Hiko2241Battery359.8 MWwithdrawnClark, Nevada
Onyx2291Solar+Battery353.1 MWwithdrawnClark, Nevada
NV Queue Project Company 177 — Solar in Clark, NevadaCompany 177Solar350.0 MWwithdrawnClark, Nevada
KAWICH2147Solar+Battery350.0 MWactiveClark, Nevada
NV Queue Project Company 173 — Solar+Battery in Clark, NevadaCompany 173Solar+Battery350.0 MWsuspendedClark, Nevada
NV Queue Project Company 242 — Battery in Clark, NevadaCompany 242Battery350.0 MWactiveClark, Nevada

Top developers

Developer attribution is not yet resolved for this set.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: California ISO — public interconnection queue; U.S. EIA — Form EIA-860M generator inventory (operating + planned); ladwp-oasis; Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; nvenergy-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.