NY Wind - Pilgrim CSR (1503)

NY Wind - Pilgrim CSR is a 1,400.0 MW other interconnection project in Suffolk County, New York with a current status of withdrawn. It is proposed to connect at Pilgrim 138 kV.

1,400.0 MWCapacity
WithdrawnStatus
KMarket
OtherTechnology

Project facts

Canonical nameNY Wind - Pilgrim CSR
Queue ID1503
Statuswithdrawn
Source status0
MarketK
TechnologyOther
Capacity1,400.0 MW
StateNew York
CountySuffolk County
Point of interconnectionPilgrim 138 kV
Requested (queue) date2023-01-15
Proposed in-service date2024-05-31
Operational date
Withdrawn date
DeveloperBay State Wind
Utility / transmission ownerLIPA

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: New York ISO — interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.