Ocotillo Wind Farm 1 (Big Spring Option B) (04INR0017)

Ocotillo Wind Farm 1 (Big Spring Option B) is a 59.0 MW wind interconnection project with a current status of operational. It is proposed to connect at OWF_OWF 34.500.

59.0 MWCapacity
OperationalStatus
ERCOTMarket
WindTechnology

Project facts

Canonical nameOcotillo Wind Farm 1 (Big Spring Option B)
Queue ID04INR0017
Statusoperational
Source statusoperational
MarketERCOT
TechnologyWind
Capacity59.0 MW
State
County
Point of interconnectionOWF_OWF 34.500
Requested (queue) date2003-09-15
Proposed in-service date2008-08-01
Operational date
Withdrawn date
DeveloperTexas American Power
Utility / transmission ownerERCOT

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata