Offshore Wind (1059)
Offshore Wind is a 1,200.0 MW wind interconnection project with a current status of withdrawn. It is proposed to connect at Eversource NSTAR Pilgrim 345 kV substation.
1,200.0 MWCapacity
WithdrawnStatus
SEMAMarket
WindTechnology
Project facts
| Canonical name | Offshore Wind |
|---|---|
| Queue ID | 1059 |
| Status | withdrawn |
| Source status | W |
| Market | SEMA |
| Technology | Wind |
| Capacity | 1,200.0 MW |
| State | Massachusetts |
| County | — |
| Point of interconnection | Eversource NSTAR Pilgrim 345 kV substation |
| Requested (queue) date | 2020-09-09 |
| Proposed in-service date | 2027-11-30 |
| Operational date | — |
| Withdrawn date | 2022-12-13 |
| Developer | — |
| Utility / transmission owner | ISO-NE |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-08-04 | new_project | — | withdrawn | high |
Explore related data
Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27
Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.