Offshore Wind (909)

Offshore Wind is a 814.0 MW wind interconnection project with a current status of withdrawn. It is proposed to connect at Primary National Grid 115kV Bell Rock, alt: Eversource 115kV Wings Lane, National Grid 115kV Somerset.

814.0 MWCapacity
WithdrawnStatus
SEMAMarket
WindTechnology

Project facts

Canonical nameOffshore Wind
Queue ID909
Statuswithdrawn
Source statusW
MarketSEMA
TechnologyWind
Capacity814.0 MW
StateMassachusetts
County
Point of interconnectionPrimary National Grid 115kV Bell Rock, alt: Eversource 115kV Wings Lane, National Grid 115kV Somerset
Requested (queue) date2019-08-01
Proposed in-service date2026-05-31
Operational date
Withdrawn date2024-02-13
Developer
Utility / transmission ownerISO-NE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.