Offshore Wind w/ battery storage (632)

Offshore Wind w/ battery storage is a 880.0 MW wind interconnection project with a current status of withdrawn. It is proposed to connect at Eversource, 115kV Bourne Substation, Barnstable County, Massachusetts.

880.0 MWCapacity
WithdrawnStatus
SEMAMarket
WindTechnology

Project facts

Canonical nameOffshore Wind w/ battery storage
Queue ID632
Statuswithdrawn
Source statusW
MarketSEMA
TechnologyWind
Capacity880.0 MW
StateMassachusetts
County
Point of interconnectionEversource, 115kV Bourne Substation, Barnstable County, Massachusetts
Requested (queue) date2017-04-05
Proposed in-service date2024-12-06
Operational date
Withdrawn date2020-01-23
Developer
Utility / transmission ownerISO-NE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.