Oklaunion 345kV Substation (GEN-2022-191)

Oklaunion 345kV Substation is a 200.0 MW wind interconnection project in Baylor, Texas with a current status of withdrawn. It is proposed to connect at Oklaunion 345kV Substation.

200.0 MWCapacity
WithdrawnStatus
TXMarket
WindTechnology

Project facts

Canonical nameOklaunion 345kV Substation
Queue IDGEN-2022-191
Statuswithdrawn
Source statusWITHDRAWN
MarketTX
TechnologyWind
Capacity200.0 MW
StateTexas
CountyBaylor
Point of interconnectionOklaunion 345kV Substation
Requested (queue) date2023-02-28
Proposed in-service date2027-12-15
Operational date
Withdrawn date2023-05-31
Developer
Utility / transmission ownerAEP

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-28
Data last materially changed2026-08-28
Page data generated2026-08-28

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata