Olive-Dumont 345kV (O65)

Olive-Dumont 345kV is a 650.0 MW other interconnection project in St. Joseph, Indiana with a current status of withdrawn.

650.0 MWCapacity
WithdrawnStatus
Market
OtherTechnology

Project facts

Canonical nameOlive-Dumont 345kV
Queue IDO65
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyOther
Capacity650.0 MW
StateIndiana
CountySt. Joseph
Point of interconnection
Requested (queue) date2005-07-29
Proposed in-service date2010-07-01
Operational date
Withdrawn date2005-10-17
Developer
Utility / transmission ownerAEP

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata