OR Queue Project 21-103 — Battery in Clackamas, Oregon

OR Queue Project 21-103 — Battery in Clackamas, Oregon is a 200.0 MW battery interconnection project in Clackamas, Oregon with a current status of active. It is proposed to connect at Carver Substation.

200.0 MWCapacity
ActiveStatus
ORMarket
BatteryTechnology

Project facts

Canonical nameOR Queue Project 21-103 — Battery in Clackamas, Oregon
Queue ID21-103
Statusactive
Source statusFacility Study Complete
MarketOR
TechnologyBattery
Capacity200.0 MW
StateOregon
CountyClackamas
Point of interconnectionCarver Substation
Requested (queue) date2021-05-26
Proposed in-service date2024-01-01
Operational date
Withdrawn date
Developer
Utility / transmission ownerPortland General Electric

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-05new_projectactivehigh

Explore related data

Source last checked2026-08-05
Data last materially changed2026-08-05
Page data generated2026-08-28

Provenance: pge-or-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata