OR Queue Project 23-239 — Battery in Multnomah, Oregon
OR Queue Project 23-239 — Battery in Multnomah, Oregon is a 200.0 MW battery interconnection project in Multnomah, Oregon with a current status of active. It is proposed to connect at Rivergate Substation 230kV.
200.0 MWCapacity
ActiveStatus
ORMarket
BatteryTechnology
Project facts
| Canonical name | OR Queue Project 23-239 — Battery in Multnomah, Oregon |
|---|---|
| Queue ID | 23-239 |
| Status | active |
| Source status | Transitional Cluster Study |
| Market | OR |
| Technology | Battery |
| Capacity | 200.0 MW |
| State | Oregon |
| County | Multnomah |
| Point of interconnection | Rivergate Substation 230kV |
| Requested (queue) date | — |
| Proposed in-service date | 2028-12-31 |
| Operational date | — |
| Withdrawn date | — |
| Developer | — |
| Utility / transmission owner | Portland General Electric |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-08-05 | new_project | — | active | high |
Explore related data
Source last checked2026-08-05
Data last materially changed2026-08-05
Page data generated2026-08-27
Provenance: pge-or-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata