OR Queue Project G0300 — Wind in Crook, Oregon
OR Queue Project G0300 — Wind in Crook, Oregon is a 104.0 MW wind interconnection project in Crook, Oregon with a current status of withdrawn. It is proposed to connect at At a point on BPA's Brasada-Harney 115 kV transmission line.
104.0 MWCapacity
WithdrawnStatus
ORMarket
WindTechnology
Project facts
| Canonical name | OR Queue Project G0300 — Wind in Crook, Oregon |
|---|---|
| Queue ID | G0300 |
| Status | withdrawn |
| Source status | WITHDRAWN |
| Market | OR |
| Technology | Wind |
| Capacity | 104.0 MW |
| State | Oregon |
| County | Crook |
| Point of interconnection | At a point on BPA's Brasada-Harney 115 kV transmission line |
| Requested (queue) date | 2007-12-18 |
| Proposed in-service date | 2010-10-30 |
| Operational date | — |
| Withdrawn date | — |
| Developer | — |
| Utility / transmission owner | Bonneville Power Administration |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-08-04 | new_project | — | withdrawn | high |
Explore related data
Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27
Provenance: bpa-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata