OR Queue Project G0725 — Battery in Coos & Curry, Oregon

OR Queue Project G0725 — Battery in Coos & Curry, Oregon is a 600.0 MW battery interconnection project in Coos & Curry, Oregon with a current status of withdrawn. It is proposed to connect at Fairview 230 kV Substation.

600.0 MWCapacity
WithdrawnStatus
ORMarket
BatteryTechnology

Project facts

Canonical nameOR Queue Project G0725 — Battery in Coos & Curry, Oregon
Queue IDG0725
Statuswithdrawn
Source statusWITHDRAWN
MarketOR
TechnologyBattery
Capacity600.0 MW
StateOregon
CountyCoos & Curry
Point of interconnectionFairview 230 kV Substation
Requested (queue) date2022-01-26
Proposed in-service date2027-12-10
Operational date
Withdrawn date
Developer
Utility / transmission ownerBonneville Power Administration

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-28

Provenance: bpa-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.