OR Queue Project G1019 — Solar in Klamath, Oregon

OR Queue Project G1019 — Solar in Klamath, Oregon is a 500.0 MW solar interconnection project in Klamath, Oregon with a current status of withdrawn. It is proposed to connect at LaPine-Chiloquin No 1 230kV line..

500.0 MWCapacity
WithdrawnStatus
ORMarket
SolarTechnology

Project facts

Canonical nameOR Queue Project G1019 — Solar in Klamath, Oregon
Queue IDG1019
Statuswithdrawn
Source statusWITHDRAWN
MarketOR
TechnologySolar
Capacity500.0 MW
StateOregon
CountyKlamath
Point of interconnectionLaPine-Chiloquin No 1 230kV line.
Requested (queue) date2023-11-21
Proposed in-service date2030-11-15
Operational date
Withdrawn date
Developer
Utility / transmission ownerBonneville Power Administration

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-28

Provenance: bpa-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata