OR Queue Project OCS010 — Solar in Wallowa, Oregon

OR Queue Project OCS010 — Solar in Wallowa, Oregon is a 1.9 MW solar interconnection project in Wallowa, Oregon with a current status of withdrawn. It is proposed to connect at Circuit 4W8 out of Enterprise substation.

1.9 MWCapacity
WithdrawnStatus
ORMarket
SolarTechnology

Project facts

Canonical nameOR Queue Project OCS010 — Solar in Wallowa, Oregon
Queue IDOCS010
Statuswithdrawn
Source statusWithdrawn
MarketOR
TechnologySolar
Capacity1.9 MW
StateOregon
CountyWallowa
Point of interconnectionCircuit 4W8 out of Enterprise substation
Requested (queue) date2020-02-14
Proposed in-service date2021-07-01
Operational date
Withdrawn date
Developer
Utility / transmission ownerPacifiCorp

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-03new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-27

Provenance: pacificorp-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata