OR Queue Project OCS031 — Solar in Linn, Oregon

OR Queue Project OCS031 — Solar in Linn, Oregon is a 1.8 MW solar interconnection project in Linn, Oregon with a current status of withdrawn. It is proposed to connect at Circuit 4M70 out of New Lyons substation.

1.8 MWCapacity
WithdrawnStatus
ORMarket
SolarTechnology

Project facts

Canonical nameOR Queue Project OCS031 — Solar in Linn, Oregon
Queue IDOCS031
Statuswithdrawn
Source statusWithdrawn
MarketOR
TechnologySolar
Capacity1.8 MW
StateOregon
CountyLinn
Point of interconnectionCircuit 4M70 out of New Lyons substation
Requested (queue) date2020-06-01
Proposed in-service date2020-12-31
Operational date
Withdrawn date
Developer
Utility / transmission ownerPacifiCorp

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-03new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-27

Provenance: pacificorp-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata