Oriole Solar (28INR0008)

Oriole Solar is a 503.9 MW solar interconnection project in Knox, Texas with a current status of operational. It is proposed to connect at Tap 345kV 6076 Foxtail - 60791 Perigee .

503.9 MWCapacity
OperationalStatus
KnoxMarket
SolarTechnology

Project facts

Canonical nameOriole Solar
Queue ID28INR0008
Statusoperational
Source statusSS Completed, FIS Started, IA
MarketKnox
TechnologySolar
Capacity503.9 MW
StateTexas
CountyKnox
Point of interconnectionTap 345kV 6076 Foxtail - 60791 Perigee
Requested (queue) date2023-05-15
Proposed in-service date
Operational date2028-12-29
Withdrawn date
DeveloperRolling Plains Solar
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-28

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata