Other_ (J3689)

Other_ is a 200.0 MW battery interconnection project in Montgomery, Indiana with a current status of withdrawn. It is proposed to connect at Other_.

200.0 MWCapacity
WithdrawnStatus
Market
BatteryTechnology

Project facts

Canonical nameOther_
Queue IDJ3689
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyBattery
Capacity200.0 MW
StateIndiana
CountyMontgomery
Point of interconnectionOther_
Requested (queue) date2024-04-16
Proposed in-service date2028-09-30
Operational date2028-09-30
Withdrawn date2025-12-23
Developer
Utility / transmission ownerDuke Energy Progress

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-28
Data last materially changed2026-08-28
Page data generated2026-08-28

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.