PACE Queue Project C1-39 — Solar+Battery in Washington, Utah

PACE Queue Project C1-39 — Solar+Battery in Washington, Utah is a 300.0 MW solar+battery interconnection project in Washington, Utah with a current status of active. It is proposed to connect at Red Butte – Three Peaks – Sigurd transmission line.

300.0 MWCapacity
ActiveStatus
PACEMarket
Solar+BatteryTechnology

Project facts

Canonical namePACE Queue Project C1-39 — Solar+Battery in Washington, Utah
Queue IDC1-39
Statusactive
Source statusIn Progress
MarketPACE
TechnologySolar+Battery
Capacity300.0 MW
StateUtah
CountyWashington
Point of interconnectionRed Butte – Three Peaks – Sigurd transmission line
Requested (queue) date2021-05-14
Proposed in-service date2028-12-29
Operational date
Withdrawn date
Developer
Utility / transmission ownerPacifiCorp

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-03new_projectactivehigh

Explore related data

Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-27

Provenance: pacificorp-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata