PACE Queue Project C3-141 — Solar+Battery in Iron, Utah

PACE Queue Project C3-141 — Solar+Battery in Iron, Utah is a 49.9 MW solar+battery interconnection project in Iron, Utah with a current status of withdrawn. It is proposed to connect at Enterprise Valley substation.

49.9 MWCapacity
WithdrawnStatus
PACEMarket
Solar+BatteryTechnology

Project facts

Canonical namePACE Queue Project C3-141 — Solar+Battery in Iron, Utah
Queue IDC3-141
Statuswithdrawn
Source statusWithdrawn
MarketPACE
TechnologySolar+Battery
Capacity49.9 MW
StateUtah
CountyIron
Point of interconnectionEnterprise Valley substation
Requested (queue) date2023-05-15
Proposed in-service date2028-12-29
Operational date
Withdrawn date
Developer
Utility / transmission ownerPacifiCorp

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-03new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-28

Provenance: pacificorp-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata