PACW Queue Project C1-20 — Solar+Battery in Linn, Oregon

PACW Queue Project C1-20 — Solar+Battery in Linn, Oregon is a 199.0 MW solar+battery interconnection project in Linn, Oregon with a current status of suspended. It is proposed to connect at Diamond Hill substation.

199.0 MWCapacity
SuspendedStatus
PACWMarket
Solar+BatteryTechnology

Project facts

Canonical namePACW Queue Project C1-20 — Solar+Battery in Linn, Oregon
Queue IDC1-20
Statussuspended
Source statusSuspended
MarketPACW
TechnologySolar+Battery
Capacity199.0 MW
StateOregon
CountyLinn
Point of interconnectionDiamond Hill substation
Requested (queue) date2021-05-07
Proposed in-service date2025-12-31
Operational date
Withdrawn date
Developer
Utility / transmission ownerPacifiCorp

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-03new_projectsuspendedhigh

Explore related data

Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-27

Provenance: pacificorp-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata