PACW Queue Project C2-04 — Battery in Klamath, Oregon
PACW Queue Project C2-04 — Battery in Klamath, Oregon is a 199.9 MW battery interconnection project in Klamath, Oregon with a current status of active. It is proposed to connect at Snow Goose substation.
199.9 MWCapacity
ActiveStatus
PACWMarket
BatteryTechnology
Project facts
| Canonical name | PACW Queue Project C2-04 — Battery in Klamath, Oregon |
|---|---|
| Queue ID | C2-04 |
| Status | active |
| Source status | In Progress |
| Market | PACW |
| Technology | Battery |
| Capacity | 199.9 MW |
| State | Oregon |
| County | Klamath |
| Point of interconnection | Snow Goose substation |
| Requested (queue) date | 2022-04-01 |
| Proposed in-service date | 2026-12-15 |
| Operational date | — |
| Withdrawn date | — |
| Developer | — |
| Utility / transmission owner | PacifiCorp |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-08-03 | new_project | — | active | high |
Explore related data
Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-27
Provenance: pacificorp-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata