PACW Queue Project C4-054 — Solar+Battery in Deschutes, Oregon

PACW Queue Project C4-054 — Solar+Battery in Deschutes, Oregon is a 19.9 MW solar+battery interconnection project in Deschutes, Oregon with a current status of withdrawn. It is proposed to connect at Cove – Pelton Rereg transmission line.

19.9 MWCapacity
WithdrawnStatus
PACWMarket
Solar+BatteryTechnology

Project facts

Canonical namePACW Queue Project C4-054 — Solar+Battery in Deschutes, Oregon
Queue IDC4-054
Statuswithdrawn
Source statusWithdrawn
MarketPACW
TechnologySolar+Battery
Capacity19.9 MW
StateOregon
CountyDeschutes
Point of interconnectionCove – Pelton Rereg transmission line
Requested (queue) date2024-05-15
Proposed in-service date2028-12-31
Operational date
Withdrawn date
Developer
Utility / transmission ownerPacifiCorp

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-03new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-27

Provenance: pacificorp-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata