PACW Queue Project FT032 — Battery in Multnomah, Oregon
PACW Queue Project FT032 — Battery in Multnomah, Oregon is a 1.9 MW battery interconnection project in Multnomah, Oregon with a current status of withdrawn. It is proposed to connect at Circuit 5P474 out of Columbia substation.
1.9 MWCapacity
WithdrawnStatus
PACWMarket
BatteryTechnology
Project facts
| Canonical name | PACW Queue Project FT032 — Battery in Multnomah, Oregon |
|---|---|
| Queue ID | FT032 |
| Status | withdrawn |
| Source status | Withdrawn |
| Market | PACW |
| Technology | Battery |
| Capacity | 1.9 MW |
| State | Oregon |
| County | Multnomah |
| Point of interconnection | Circuit 5P474 out of Columbia substation |
| Requested (queue) date | 2025-12-02 |
| Proposed in-service date | — |
| Operational date | — |
| Withdrawn date | — |
| Developer | — |
| Utility / transmission owner | PacifiCorp |
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-08-03 | new_project | — | withdrawn | high |
Explore related data
Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-27
Provenance: pacificorp-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.