PACW Queue Project T2-070 — Solar+Battery in Harney, Oregon

PACW Queue Project T2-070 — Solar+Battery in Harney, Oregon is a 640.0 MW solar+battery interconnection project in Harney, Oregon with a current status of active. It is proposed to connect at Burns – Summer Lake transmission line.

640.0 MWCapacity
ActiveStatus
PACWMarket
Solar+BatteryTechnology

Project facts

Canonical namePACW Queue Project T2-070 — Solar+Battery in Harney, Oregon
Queue IDT2-070
Statusactive
Source statusIn Progress
MarketPACW
TechnologySolar+Battery
Capacity640.0 MW
StateOregon
CountyHarney
Point of interconnectionBurns – Summer Lake transmission line
Requested (queue) date2025-09-12
Proposed in-service date2028-12-31
Operational date—
Withdrawn date—
Developer—
Utility / transmission ownerPacifiCorp

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-03new_project—activehigh

Explore related data

Source last checked2026-10-05
Data last materially changed2026-10-05
Page data generated2026-10-11

Provenance: pacificorp-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.