Palisade BESS (29INR0174)

Palisade BESS is a 153.5 MW other interconnection project in Brazoria, Texas with a current status of operational. It is proposed to connect at Hoffman (42810) - Lake Jackson (42880) 138 kV line .

153.5 MWCapacity
OperationalStatus
BrazoriaMarket
OtherTechnology

Project facts

Canonical namePalisade BESS
Queue ID29INR0174
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketBrazoria
TechnologyOther
Capacity153.5 MW
StateTexas
CountyBrazoria
Point of interconnectionHoffman (42810) - Lake Jackson (42880) 138 kV line
Requested (queue) date2025-09-23
Proposed in-service date
Operational date2029-10-01
Withdrawn date
DeveloperFlexen USA LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.