Panhandle Flagship Storage (27INR0025)

Panhandle Flagship Storage is a 371.7 MW other interconnection project in Carson, Texas with a current status of operational. It is proposed to connect at 345 kV Railhead Substation (RAILHEAD #79005).

371.7 MWCapacity
OperationalStatus
CarsonMarket
OtherTechnology

Project facts

Canonical namePanhandle Flagship Storage
Queue ID27INR0025
Statusoperational
Source statusSS Completed, FIS Started, IA
MarketCarson
TechnologyOther
Capacity371.7 MW
StateTexas
CountyCarson
Point of interconnection345 kV Railhead Substation (RAILHEAD #79005)
Requested (queue) date2023-03-13
Proposed in-service date
Operational date2031-06-30
Withdrawn date
DeveloperPanhandle Solar Group Operating Company LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.