PATTERSON PASS ENERGY CENTER (269)
PATTERSON PASS ENERGY CENTER is a 371.3 MW gas interconnection project in San Joaquin, California with a current status of withdrawn. It is proposed to connect at Tesla-Westley 230 KV lines.
371.3 MWCapacity
WithdrawnStatus
—Market
GasTechnology
Project facts
| Canonical name | PATTERSON PASS ENERGY CENTER |
|---|---|
| Queue ID | 269 |
| Status | withdrawn |
| Source status | WITHDRAWN |
| Market | — |
| Technology | Gas |
| Capacity | 371.3 MW |
| State | California |
| County | San Joaquin |
| Point of interconnection | Tesla-Westley 230 KV lines |
| Requested (queue) date | 2007-10-31 |
| Proposed in-service date | — |
| Operational date | — |
| Withdrawn date | 2011-04-07 |
| Developer | — |
| Utility / transmission owner | PGAE |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-29 | new_project | — | withdrawn | high |
Explore related data
Source last checked2026-08-28
Data last materially changed2026-08-28
Page data generated2026-08-28
Provenance: California ISO — public interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata