Pavo Creek Storage (27INR0441)

Pavo Creek Storage is a 154.2 MW other interconnection project in Milam, Texas with a current status of operational. It is proposed to connect at Tap #3659 Thorndale North - #3701 Rookie Switch 138 kV.

154.2 MWCapacity
OperationalStatus
MilamMarket
OtherTechnology

Project facts

Canonical namePavo Creek Storage
Queue ID27INR0441
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketMilam
TechnologyOther
Capacity154.2 MW
StateTexas
CountyMilam
Point of interconnectionTap #3659 Thorndale North - #3701 Rookie Switch 138 kV
Requested (queue) date2025-02-25
Proposed in-service date
Operational date2028-09-21
Withdrawn date
DeveloperPavo Creek Storage, LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.