Paxton BESS (1582)

Paxton BESS is a 3.0 MW battery interconnection project in Worcester, Massachusetts with a current status of withdrawn. It is proposed to connect at Paxton Municipal Light Department 13.8KV.

3.0 MWCapacity
WithdrawnStatus
SEMAMarket
BatteryTechnology

Project facts

Canonical namePaxton BESS
Queue ID1582
Statuswithdrawn
Source statusW
MarketSEMA
TechnologyBattery
Capacity3.0 MW
StateMassachusetts
CountyWorcester
Point of interconnectionPaxton Municipal Light Department 13.8KV
Requested (queue) date2024-07-29
Proposed in-service date2024-12-02
Operational date
Withdrawn date2025-06-13
Developer
Utility / transmission ownerISO-NE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata