Peach Bottom is a 1,499.4 MW other interconnection project in York, Pennsylvania with a current status of operational.

1,499.4 MWCapacity
OperationalStatus
PJMMarket
OtherTechnology

Project facts

Canonical namePeach Bottom
Queue ID3166_2
Statusoperational
Source status(OP) Operating
MarketPJM
TechnologyOther
Capacity1,499.4 MW
StatePennsylvania
CountyYork
Point of interconnection—
Requested (queue) date—
Proposed in-service date—
Operational date1974-07-01
Withdrawn date—
Developer—
Utility / transmission ownerConstellation Nuclear

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-02new_project—operationalhigh

Explore related data

Source last checked2026-10-02
Data last materially changed2026-10-02
Page data generated2026-10-11

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned). Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.