York County, Pennsylvania — Interconnection Projects
The interXdata warehouse tracks 105 interconnection projects in York, Pennsylvania, representing 18,369 MW of requested capacity.
105Total projects
8Active
42Operational
54Withdrawn
18,369 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Gas | 39 | 13,276 MW |
| Other | 19 | 3,698 MW |
| Solar | 37 | 702 MW |
| Battery | 10 | 692 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Peach Bottom | 3166_2 | Other | 1,499.4 MW | operational | York, Pennsylvania |
| Peach Bottom | 3166_3 | Other | 1,377.0 MW | operational | York, Pennsylvania |
| Brunner Island 230kV | G33 | Gas | 1,200.0 MW | withdrawn | York, Pennsylvania |
| TMI-Peach Bottom 500kV | H14 | Gas | 1,060.0 MW | withdrawn | York, Pennsylvania |
| Brunner Island | 3140_3 | Gas | 847.8 MW | operational | York, Pennsylvania |
| Peach Bottom-TMI #1 500kV I | X4-020 | Gas | 800.0 MW | withdrawn | York, Pennsylvania |
| Peach Bottom 500kV | Y3-043 | Gas | 760.0 MW | operational | York, Pennsylvania |
| Graceton 230kV | X3-068 | Gas | 678.0 MW | withdrawn | York, Pennsylvania |
| TMI - Juniata 500kV | G32 | Gas | 675.0 MW | withdrawn | York, Pennsylvania |
| Graceton 230kV | V4-002 | Gas | 575.0 MW | withdrawn | York, Pennsylvania |
| Graceton-Nottingham 230kV | N01 | Gas | 550.0 MW | withdrawn | York, Pennsylvania |
| Graceton 230kV | P05 | Gas | 550.0 MW | withdrawn | York, Pennsylvania |
| Peach Bottom | N02 | Gas | 550.0 MW | withdrawn | York, Pennsylvania |
| Peach Bottom 500kV | S22 | Gas | 550.0 MW | withdrawn | York, Pennsylvania |
| Graceton 230kV | S23 | Gas | 550.0 MW | withdrawn | York, Pennsylvania |
| Peach Bottom 500kV | P04 | Gas | 550.0 MW | operational | York, Pennsylvania |
| Graceton 230kV | L06 | Gas | 550.0 MW | withdrawn | York, Pennsylvania |
| York Energy Center | 55524_STG2 | Gas | 419.6 MW | operational | York, Pennsylvania |
| Brunner Island | 3140_2 | Gas | 405.0 MW | operational | York, Pennsylvania |
| Brunner Island | 3140_1 | Gas | 363.3 MW | operational | York, Pennsylvania |
| Peach Bottom-TMI #2 500kV II | X4-021 | Gas | 320.0 MW | withdrawn | York, Pennsylvania |
| York Energy Center | 55524_CTG6 | Gas | 234.9 MW | operational | York, Pennsylvania |
| York Energy Center | 55524_CTG5 | Gas | 234.9 MW | operational | York, Pennsylvania |
| York Energy Center | 55524_STG1 | Gas | 200.0 MW | operational | York, Pennsylvania |
| Queen Street 115 kV | AF2-195 | Battery | 171.7 MW | withdrawn | York, Pennsylvania |
| Muddy Run 230kV | B28 | Other | 160.0 MW | operational | York, Pennsylvania |
| Peach Bottom | Q47 | Other | 140.0 MW | operational | York, Pennsylvania |
| Peach Bottom | V4-045 | Other | 133.8 MW | operational | York, Pennsylvania |
| Roundtop 115 kV | AH2-335 | Battery | 130.0 MW | withdrawn | York, Pennsylvania |
| York 115kV | U4-004 | Gas | 120.0 MW | withdrawn | York, Pennsylvania |
| York Energy Center | 55524_CTG1 | Gas | 120.0 MW | operational | York, Pennsylvania |
| York Energy Center | 55524_CTG2 | Gas | 120.0 MW | operational | York, Pennsylvania |
| Peach Bottom 500kV | AA1-034 | Gas | 120.0 MW | operational | York, Pennsylvania |
| York Energy Center | 55524_CTG3 | Gas | 120.0 MW | operational | York, Pennsylvania |
| York Storage 115 kV | AG1-248 | Battery | 119.0 MW | withdrawn | York, Pennsylvania |
| North Hanover-Gitts Run 115 kV | AG1-465 | Battery | 100.0 MW | withdrawn | York, Pennsylvania |
| Zions View-Smith Street 115 kV | AF2-213 | Battery | 81.2 MW | withdrawn | York, Pennsylvania |
| Zion View - Middletown 115 kV | AE1-129 | Solar | 79.6 MW | suspended | York, Pennsylvania |
| Strinestown Solar | 68969_ENX39 | Solar | 79.6 MW | active | York, Pennsylvania |
| Dover Solar (PA) | 68995_ENX38 | Solar | 75.0 MW | active | York, Pennsylvania |
| Peach Bottom 500kV | G46 | Other | 70.0 MW | operational | York, Pennsylvania |
| Brunner Island 13.8 kV | AF2-228 | Solar | 61.0 MW | withdrawn | York, Pennsylvania |
| Jackson-Three Mile Island 230 kV | AE2-211 | Solar | 55.0 MW | active | York, Pennsylvania |
| Pixelle Specialty Solutions LLC - Spring | 50397_GEN5 | Other | 45.9 MW | operational | York, Pennsylvania |
| Peach Bottom 500kV | AB2-175 | Other | 44.0 MW | operational | York, Pennsylvania |
| Pixelle Specialty Solutions LLC - Spring | 50397_GEN6 | Other | 39.1 MW | operational | York, Pennsylvania |
| York County Resource Recovery | 50215_GEN1 | Other | 36.5 MW | operational | York, Pennsylvania |
| Tolna | 3116_1 | Other | 27.0 MW | operational | York, Pennsylvania |
| Tolna | 3116_2 | Other | 27.0 MW | operational | York, Pennsylvania |
| PJM Queue Project AH1-046 — Solar in York, Pennsylvania | AH1-046 | Solar | 25.0 MW | withdrawn | York, Pennsylvania |
| Peach Bottom 500 kV | AH1-046 - moved to TC2 | Solar | 25.0 MW | withdrawn | York, Pennsylvania |
| Cooper | W1-010 | Solar | 20.0 MW | withdrawn | York, Pennsylvania |
| Cottontail Solar 1 | 65076_PACT1 | Solar | 20.0 MW | operational | York, Pennsylvania |
| Cottontail Solar 8 | 65082_PACT8 | Solar | 20.0 MW | operational | York, Pennsylvania |
| Hokes-Jackson 69 kV | AE1-185 | Solar | 20.0 MW | operational | York, Pennsylvania |
| Five Fork 115kV | AH1-622 | Solar | 20.0 MW | withdrawn | York, Pennsylvania |
| Tolna 115 kV | AF2-383 | Solar | 20.0 MW | withdrawn | York, Pennsylvania |
| Jackson-Three Mile Island 230 kV III | AG1-053 | Battery | 20.0 MW | withdrawn | York, Pennsylvania |
| Cottontail Solar 2 | 65077_PACT2 | Solar | 20.0 MW | operational | York, Pennsylvania |
| Hokes-Grantley 69 kV | AD2-116 | Solar | 20.0 MW | operational | York, Pennsylvania |
Top developers
| Developer (canonical) | Projects | Capacity |
|---|---|---|
| Calpine Energy Services, L.P. | 1 | 25 MW |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Get an alert when a new project is proposed in York County.