Pecos Flats Wind I (30INR0131)
Pecos Flats Wind I is a 506.9 MW other interconnection project in Pecos, Texas with a current status of active. It is proposed to connect at Tap Bottlebrush (38441) to White Baker (38435) 345kV Line (TNMP).
506.9 MWCapacity
ActiveStatus
PecosMarket
OtherTechnology
Project facts
| Canonical name | Pecos Flats Wind I |
|---|---|
| Queue ID | 30INR0131 |
| Status | active |
| Source status | SS Started, FIS Started, No IA |
| Market | Pecos |
| Technology | Other |
| Capacity | 506.9 MW |
| State | Texas |
| County | Pecos |
| Point of interconnection | Tap Bottlebrush (38441) to White Baker (38435) 345kV Line (TNMP) |
| Requested (queue) date | 2026-07-22 |
| Proposed in-service date | 2030-06-29 |
| Operational date | — |
| Withdrawn date | — |
| Developer | Pecos Flats Wind II, LLC |
| Utility / transmission owner | ERCOT |
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-08-31 | new_project | — | active | high |
Explore related data
Source last checked2026-09-30
Data last materially changed2026-09-30
Page data generated2026-10-11
Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.