Penelope Solar (28INR0404)

Penelope Solar is a 97.8 MW solar interconnection project in Hill, Texas with a current status of operational. It is proposed to connect at New sub in the 234 Chatt - 3473 Ash Creek 138kV line.

97.8 MWCapacity
OperationalStatus
HillMarket
SolarTechnology

Project facts

Canonical namePenelope Solar
Queue ID28INR0404
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketHill
TechnologySolar
Capacity97.8 MW
StateTexas
CountyHill
Point of interconnectionNew sub in the 234 Chatt - 3473 Ash Creek 138kV line
Requested (queue) date2025-07-21
Proposed in-service date
Operational date2029-09-24
Withdrawn date
DeveloperAsh Creek
Utility / transmission ownerERCOT

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.