Perkins Park 12.47 kV (AG2-203)

Perkins Park 12.47 kV is a 20.0 MW battery interconnection project in City Of Lynchburg, Virginia with a current status of withdrawn.

20.0 MWCapacity
WithdrawnStatus
—Market
BatteryTechnology

Project facts

Canonical namePerkins Park 12.47 kV
Queue IDAG2-203
Statuswithdrawn
Source statusWithdrawn
Market—
TechnologyBattery
Capacity20.0 MW
StateVirginia
CountyCity Of Lynchburg
Point of interconnection—
Requested (queue) date2021-03-04
Proposed in-service date2022-10-31
Operational date—
Withdrawn date2024-12-18
Developer—
Utility / transmission ownerAEP

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_project—withdrawnhigh

Explore related data

Source last checked2026-11-26
Data last materially changed2026-11-26
Page data generated2026-11-26

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.