Pethrus BESS (26INR0280)

Pethrus BESS is a 174.1 MW other interconnection project in Wichita, Texas with a current status of operational. It is proposed to connect at Tap Wichita Falls Switch (#1464) – North Star (#1467) 138 kV Line.

174.1 MWCapacity
OperationalStatus
WichitaMarket
OtherTechnology

Project facts

Canonical namePethrus BESS
Queue ID26INR0280
Statusoperational
Source statusSS Completed, FIS Completed, No IA
MarketWichita
TechnologyOther
Capacity174.1 MW
StateTexas
CountyWichita
Point of interconnectionTap Wichita Falls Switch (#1464) – North Star (#1467) 138 kV Line
Requested (queue) date2023-09-23
Proposed in-service date
Operational date2029-03-03
Withdrawn date
DeveloperPethrus BESS, LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.