Pianissimo BESS II (26INR0329)

Pianissimo BESS II is a 202.0 MW other interconnection project in Wise, Texas with a current status of operational. It is proposed to connect at Tap 138kV 685 LEO - 587 GREENWOOD.

202.0 MWCapacity
OperationalStatus
WiseMarket
OtherTechnology

Project facts

Canonical namePianissimo BESS II
Queue ID26INR0329
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketWise
TechnologyOther
Capacity202.0 MW
StateTexas
CountyWise
Point of interconnectionTap 138kV 685 LEO - 587 GREENWOOD
Requested (queue) date2024-11-19
Proposed in-service date
Operational date2027-12-31
Withdrawn date
DeveloperPianissimo Storage, LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata