Piedra Solar (25INR0168)

Piedra Solar is a 281.7 MW solar interconnection project in Freestone, Texas with a current status of operational. It is proposed to connect at Tap 345-kV line Navarro (68091) – Limestone (46020)) .

281.7 MWCapacity
OperationalStatus
FreestoneMarket
SolarTechnology

Project facts

Canonical namePiedra Solar
Queue ID25INR0168
Statusoperational
Source statusSS Completed, FIS Completed, IA
MarketFreestone
TechnologySolar
Capacity281.7 MW
StateTexas
CountyFreestone
Point of interconnectionTap 345-kV line Navarro (68091) – Limestone (46020))
Requested (queue) date2022-09-02
Proposed in-service date—
Operational date2027-01-15
Withdrawn date—
DeveloperPiedra Solar, LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-31operational_date2026-12-222027-01-15medium
2026-07-31new_project—operationalhigh

Explore related data

Source last checked2026-09-30
Data last materially changed2026-09-30
Page data generated2026-10-12

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.