Piney River VA BESS 1 (70551_90915)

Piney River VA BESS 1 is a 4.0 MW battery interconnection project in Nelson, Virginia with a current status of active.

4.0 MWCapacity
ActiveStatus
PJMMarket
BatteryTechnology

Project facts

Canonical namePiney River VA BESS 1
Queue ID70551_90915
Statusactive
Source status(V) Under construction, more than 50 percent complete
MarketPJM
TechnologyBattery
Capacity4.0 MW
StateVirginia
CountyNelson
Point of interconnection—
Requested (queue) date—
Proposed in-service date2026-11-01
Operational date—
Withdrawn date—
Developer—
Utility / transmission ownerPiney River VA BESS 1 LLC

What changed

ObservedFieldOld valueNew valueMateriality
2026-11-01new_project—activehigh

Explore related data

Source last checked2026-11-01
Data last materially changed2026-11-01
Page data generated2026-11-26

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned). Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.