PINTO PASS (1460)
PINTO PASS is a 20.0 MW battery interconnection project in Contra Costa, California with a current status of withdrawn. It is proposed to connect at Christie Substation 60kV.
20.0 MWCapacity
WithdrawnStatus
—Market
BatteryTechnology
Project facts
| Canonical name | PINTO PASS |
|---|---|
| Queue ID | 1460 |
| Status | withdrawn |
| Source status | WITHDRAWN |
| Market | — |
| Technology | Battery |
| Capacity | 20.0 MW |
| State | California |
| County | Contra Costa |
| Point of interconnection | Christie Substation 60kV |
| Requested (queue) date | 2018-04-16 |
| Proposed in-service date | — |
| Operational date | — |
| Withdrawn date | 2022-09-01 |
| Developer | — |
| Utility / transmission owner | PGAE |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-29 | new_project | — | withdrawn | high |
Explore related data
Source last checked2026-08-28
Data last materially changed2026-08-28
Page data generated2026-08-28
Provenance: California ISO — public interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata