PJM Queue Project AG2-053 — Solar in Fulton, Ohio

PJM Queue Project AG2-053 — Solar in Fulton, Ohio is a 300.0 MW solar interconnection project in Fulton, Ohio with a current status of withdrawn. It is proposed to connect at Fulton 138 kV.

300.0 MWCapacity
WithdrawnStatus
PJMMarket
SolarTechnology

Project facts

Canonical namePJM Queue Project AG2-053 — Solar in Fulton, Ohio
Queue IDAG2-053
Statuswithdrawn
Source statuswithdrawn
MarketPJM
TechnologySolar
Capacity300.0 MW
StateOhio
CountyFulton
Point of interconnectionFulton 138 kV
Requested (queue) date2020-12-02
Proposed in-service date2024-09-25
Operational date
Withdrawn date2025-07-02
DeveloperOrchid Acres Solar Project, LLC
Utility / transmission ownerATSI

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata