PJM Queue Project AG2-595 — Solar in Marion, Ohio is a 65.0 MW solar interconnection project in Marion, Ohio with a current status of withdrawn. It is proposed to connect at LaRue - North Waldo 138 kV.
65.0 MWCapacity
WithdrawnStatus
PJMMarket
SolarTechnology
Project facts
| Canonical name | PJM Queue Project AG2-595 — Solar in Marion, Ohio |
|---|---|
| Queue ID | AG2-595 |
| Status | withdrawn |
| Source status | withdrawn |
| Market | PJM |
| Technology | Solar |
| Capacity | 65.0 MW |
| State | Ohio |
| County | Marion |
| Point of interconnection | LaRue - North Waldo 138 kV |
| Requested (queue) date | 2021-03-31 |
| Proposed in-service date | 2024-06-01 |
| Operational date | — |
| Withdrawn date | 2025-07-03 |
| Developer | Riverlake Energy, LLC |
| Utility / transmission owner | AEP |
What changed
No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.
Explore related data
Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27
Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.