PJM Queue Project AH1-686 — Gas in Lawrence, Ohio

PJM Queue Project AH1-686 — Gas in Lawrence, Ohio is a 24.0 MW gas interconnection project in Lawrence, Ohio with a current status of active. It is proposed to connect at Hanging Rock 765 kV.

24.0 MWCapacity
ActiveStatus
PJMMarket
GasTechnology

Project facts

Canonical namePJM Queue Project AH1-686 — Gas in Lawrence, Ohio
Queue IDAH1-686
Statusactive
Source statusactive
MarketPJM
TechnologyGas
Capacity24.0 MW
StateOhio
CountyLawrence
Point of interconnectionHanging Rock 765 kV
Requested (queue) date2025-04-03
Proposed in-service date
Operational date
Withdrawn date
DeveloperHanging Rock Power Company LLC
Utility / transmission ownerAEP

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata